Fulghum Fibres' Brewton Alabama chipping facility was built and started
up in 1993. The mill was one of the first super mills built by
Fulghum Fibres.
The mill processes approximately 1,000,000 tons per year with 60% pine
and 40% hardwood for Georgia Pacific. It also has a Fulghum 125'
and 155' with a Fulghum 14' x 90' drum debarker.

Pictured above is the main mill line with the control cab located on the
right.

The mill also has a small radial stacker. The stacker is fed from
the accepts conveyor after the drum screens (left center of picture).

A recent addition to the chip mill is the storage pad with the tripper
conveyor. This pad can store approximately 7,000 ton along with
2,000 tons that can be stores on the radial stacker storage pad.

One of the main focuses at each of our mills is cleanliness. A
clean mill is a safe mill.

Changing knives on the 120" Fulghum chipper. This process is done
every 4 to 8 hours depending on the specie being chipped or variances in
quality.

Unloading log trucks

The control cab is one of the most important locations in the mill as
this operator controls and monitors the incoming wood to the chipper infeed. The chipper is a Fulghum 120"-14 knife horizontal
feed bottom discharge.
|